Thursday, 23. March 2023 | SAP Garden: Glas facade closed
Glas facade closed// NEWSOur glass façade was closed in mid-March. This marks the completion of another construction phase by FRENER & REIFER. The glass outer wall encloses the ground floor as well as level 1 and level 2.The numbers:
•
716 cells with a total area of 4,938 m².
•
Production of the cells from 11/2021 - 07/2022 in the South Tyrolean factory. A separate production line had to be set up for this.
•
Assembly at the construction site in the Olympiapark München from 11/2022 - 03/2023.
•
On average, 8 fitters were working on the cell assembly.